| SOURDOUGH
RURAL FIRE DISTRICT
Special Meeting Minutes, November 24, 2003
A Special Meeting of the Sourdough Rural Fire District was called to
order by Chairman Kraft at 7:35 PM November 24, 2003. All Trustees were
present in addition to Chief Crandell and Rae senior staff J.D. Engle.
The purpose of the meeting was to discuss apparatus and facility budget
and expenditures and to determine future agenda sequence and time allocation.
No motions were made regarding budget issues. Agenda process was determined
by consensus.
Facility and Apparatus Budget discussion
The following memos and cost summaries were presented and are placed
in the record.
• "Information for SFD Trustees Regarding Facility and Apparatus
Improvement Project" by staff.
• Memorandum from Bachman on Apparatus and Facility Costs, summarized
from meeting records; facility and apparatus plans and costs from 03/01
and 04/02.
• E-mail from Crandell (11/18/03) on estimates and timelines.
The staff memo was reviewed:
Estimated Components Costs 2001 mill levy proposal
Sourdough Station: $116,661
Cottonwood Station: $65,000 (figures reflect SFD cost share)
Fire Trucks: $602,343
Estimated cost of project: $784,004 (based on 7yr. completion)
Status of Project Components and Costs to Date
Sourdough Station: $32,000 ($116,661 proposed)
Cottonwood Station: Cost at Completion $367,000 ($302,348 greater than
proposed)
Fire Trucks: Cost at completion $782,077 ($179,734 greater than proposed)
Total Estimated Project Cost - $784,004
Current Project Estimate - $1,246,425. $462,421 greater than proposed.
Expected Revenues vs. Estimated Additional Costs
Estimate of Revenue: $452,000
Estimate of Costs $387,000
Chief Crandell reported that he and Scott Mueller are in the process of
going back through the records to prepare a detailed cost analysis of
the Cottonwood Station. Costs and execution have reflected the design
criteria determined by the committee of 2 + 2 from Sourdough-Rae as outlined
in the improvement project memo.
The separate live burn and non-burn training facilities cost is currently
at $70,000 and expected to finish at c.$84,000 with SFD share at $42,000.
We noted the initial Cottonwood facility plan (3/19/01) called for the
training facility integrated with a single bay fire station for a total
cost of $130,000 (SFD share of $65,000).
Chief Crandell then related the history of the two pumper-tanker trucks
that were contracted to Matt Pace of Montana Fire Works. In February '03
SFD had been assured that the trucks would be on time and on budget. Then
the process fell apart. Truck E-7 was delivered 10/03 and E-7-2 was pulled
from the job and shipped to Spokane, after more economic cab assembly
and installation in Whitehall. Cab and Chassis costs were $115,000 each
and savings anticipated through direct SFD purchase of components were
as planned. Excessive time and labor costs where unanticipated and cause
of the overruns. Truck E-7-2 will be completed by General Fire Apparatus
in Spokane, and estimates are now being prepared to assure cost certain
assembly and delivery. Work estimated at 70hrs/week with completion in
14.5 weeks. Contingency will be to 28 weeks. Cost estimates will be presented
at December meeting. E-7-2 will be equipped with ladders, hose and some
other equipment with the help of Rae. Some other safety and rescue equipment
has already been purchased in anticipation completion.
Discussion turned to revenue. Tax-based annual revenue of $287,000 is
$47,000 greater than initial calculation in '01. Sale of 1992 Pierce will
bring $125,000. Total revenue at end of fiscal year will be $452,000.
Future cycles will produce approximately $305,000 revenue annually. Fixed
expenses will include $145,000 loan repayment, $80,000 operations, and
$54,000 safety equipment, for $279,000 expense annually. Carry over from
'03 will be $60 - 65,000.
Geddes asked staff to carefully look into future scenarios which would
produce an expense bulge that would upset this calculation. The chief
will focus on scenarios that could approach worst case. Larimer asked
for a budget spreadsheet that reflects current situation expense and revenue
and to calculate our improvement project expenses against revenue through
projection. These refinements to our budget and financial report will
be implemented at the December meeting.
Trustees discussed the pending state required audit. SFD books are in
a ready condition that will facilitate the audit and reduce audit cost.
No irregularities are anticipated.
Trustees discussed future budget demands including recruitment and retention,
land acquisition, and SFD station rehabilitation.
Agenda Sequence in Time Allocation:
Trustees discussed conduct of our regular meetings. It was generally
agreed that required business including review of the Chief's Report should
be addressed as a priority at each meeting. Chairman Kraft will call for
adjournment of the meetings at 10 PM. Bachman asked that an "agenda
review" item be placed on each meeting notice so that deviations
from agenda sequence can be discussed and resolved, and time commitment
to each item assigned. The trustees agreed to this procedure which will
be initiated at the December meeting.
The meeting was adjourned at 9:40 PM.
Submitted for approval at the December 15, regular meeting
|